>Airport Construction on Schedule

> 

>Posted: 22 Jun 2009 10:59 PM PDT

> 

>The Panama City News Herald reported that airport construction is proceeding on schedule towards a May 2010 opening.

> 

>The News Herald reported:

> 

>The new airport under construction near West Bay is proceeding on schedule and should be completed by the May 2010 target date, airport officials said Friday…

> 

>The 8,400-foot runway is now 100-percent complete, and construction teams are awaiting FAA approval before extending it to 10,000 feet. Once approval is gained, the extension should take about two months to complete, officials said.

> 

>The 120,000-square-foot airport terminal, more than twice as large as the current structure in Panama City, is now about a third complete, [Airport Executive Director Randy] Curtis said.

> 

>The $62.8 million terminal complex always has been seen as the heart of the new $318 million airport taking shape near West Bay. The old terminal was only about 57,000 square feet, Curtis said.